Dear Friends & Seniors, We are in business deal with one of our client in State of Maharashtra where civil work , construction/erection work completed approx 70 % for that client has obtained all necessary approvals from local authorities like ..
#Layout approval from Factory Inspector
#Consent to Establish from Local PCB
Now we wanted to takeover that plant & operate the same with a constraint that client can not further subleased that land to us only can rent.
My queries;
1. If land is not subleased to us then what will be impact of regulatory approvals like Factory licence, Pollution consent/ Fire NOC etc? can we obtained plant operating permits easily with this constraint?
2. During project phase factory layout approval taken by our client but now for operational phase we wanted to obtain licence to run the factory so here ....Can Inspector of Factories provides us the operating licence for that Factory considering layout approval given to client & land not subleased to us.
3. Same question for Pollution Consent to Operate...like in project phase it was granted to our client now we wanted to operate.
4. If remaining 30 % construction we need to complete then does it attract any other kind of regulatory approvals amendment..
Much appreciated for your suggestions/feedback.

From India, Mumbai
Community Support and Knowledge-base on business, career and organisational prospects and issues - Register and Log In to CiteHR and post your query, download formats and be part of a fostered community of professionals.





Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2024 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.