No Tags Found!


pon1965
604

In factories, while calculating the OT, sundays to be removed. basicwages/26/8 hrs. it should be double in India and 1.5 times in UAE
From India, Lucknow
welfareofficer
2

accoring to factories act, I agree with Mr. KTiwari's openion. Overtime is given as double the normal rate(Basic+DA) for the extra durt hours. If it is 31 days duty then one hour rate is found as A/31/8 and if it is 26 days work then one hour rate is found as A/26/8 and so on.
*Average Basic salary may be considered on monthly basis only.
venkat

From India, Bangalore
phhready
2

hi, overtime calculated with double rate of normal wages i.e. Basic+DA, my question is there no place for the allowances in Overtime?
From India, Delhi
Salah5897
I have good file for you related to overtime but an able to attached it give you email and I will mail it to you
From Bahrain
Salah5897
Please see attached file for overtime Regards Salah
From Bahrain
Attached Files (Download Requires Membership)
File Type: xls Overtime.xls (33.5 KB, 2164 views)

abbasiti
517

Dear All,

As per Factories Act 1948 calculation of overtime wages is as follows.

Upto 9 hrs per day or 48 hrs per week, it is normal rate. In excess, the rate will be doubled.

Accordingly calculate the difference between the scheduled working hours and the hours secified above. For the difference the OT payment will be @single rate and in excess double. If there is any difference between the calculation on daily and weekly basis, whichever is beneficial to employee has to be paid.

For example: A company woks 6 days in a week with a uniform working time of seven and half hrs per day (8hrs including 30 minutes break). Let a worker works for 2.5 hrs extra, i.e total 10 hrs in a day, whose per hour remuneration is Rs.30/. Then the over time payment calculation will be as follows.

1) Daily basis : Scheduled time - 7.5 hrs

OT time @ normal rate - 9 -7.5 = 1.5 hrs

OT payment - 1.5 x 30 = Rs. 45 - (A)

OT time @ double rate - 10 - 9 = 1 hr

OT payment - 1 x 30x2 = Rs. 60 - (B)

Total - 45+60=105/-

2) Weekly basis : Scheduled time - 7.5 x 6 = 45 hrs

OT time @ normal rate - 47.5 -45 = 2.5 hrs

OT payment - 2.5 x 30 = Rs. 75 - (A)

OT time @ double rate - 47.5 - 48 = NA

OT payment - 0 x 30x2 = Rs. 0 - (B)

Total - 75+0=75/-

Whichever high is Rs. 105 (daily basis)

If the above worker works additional 2.5 hrs each for three days in the same week, then the calculation will be as follows.

1) Daily basis : Scheduled time - 7.5 hrs

OT time @ normal rate - 9 -7.5 = 1.5 hrs

OT payment - 1.5x3 x 30 = Rs. 135 - (A)

OT time @ double rate - 10 - 9 = 1 hr

OT payment - 1x3 x 30x2 = Rs. 180 - (B)

Total - 135+180=315/-

2) Weekly basis : Scheduled time - 7.5 x 6 = 45 hrs

OT time @ normal rate - 48-45 = 3 hrs

OT payment - 3 x 30 = Rs. 90 - (A)

OT time @ double rate - 52.5 - 48 = 4.5 hrs

OT payment - 4.5 x 30x2 = Rs. 270 - (B)

Total - 90+270=360/-

Whichever high is Rs. 360 (weekly basis)

Abbas.P.S

From India, Bangalore
Manjunath.HR
Hi,
Formula for overtime calculation is wages which they get per day/8*No.of Hrs.OT*2.
Thanks and Regards
Manjunath
Human Resources
PSK Engg.Pvt.Ltd
Mob:9980342847
more at https://www.citehr.com/69550-overtim...#ixzz16NdpxULa

From India, Kochi
abbasiti
517

Dear Manjunath,
As per the Factories Act I have funished the details on calculation of overtime payment. Accordingly the difference between 9hrs per day and the daily scheduled time or 48hrs and the weekly scheduled time, as the case may be; normal wages will be paid. Beyond this, it will be double. i.e. the overtime payment will be a mixture of normal and double rates.
But according to you it is double of the normal rate for the whole overtime. Please share that how we can byepass the Factory Act and what is the alternate legislation for your calculation?
Abbas.P.S

From India, Bangalore
maersk pakistan pvt ltd
i want to know that if i work on monday tuesday and wednesday from 9am to 9pm daily and after that i take leave from company from my annual leaves so how my overtime will be calcualte please reply
From Pakistan, Karachi
Gupta VK
148

Dear Concerned,
As per Factories Act, we can get OT work done only for one hour daily at the maximum and payment will be for two hours (i.e. double).
Calculations: His Total Wages (All Inclusive)/208xOT Hoursx2. (here 208= 26daysx8Hours)
This Payment of OT will attract ESI Contribution(if applicable) and not PF Contribution.
V K Gupta

From India, Panipat
Community Support and Knowledge-base on business, career and organisational prospects and issues - Register and Log In to CiteHR and post your query, download formats and be part of a fostered community of professionals.






Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2024 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.