Is BOCW CESS applicable for Construction activities inside the Plant Premises of Operation Power Plant Units?

Since the Plant is operational and fall under the Provision of Factory Act, 1948; exclusion of BOCW CESS for Construction inside the Plant Premises can be done in line with the definition stated in Section 2(d).

From India, Chandigarh
There is a Supreme Court decision that already states that the act applies to projects done inside an existing factory. Please read the judgement to see how it applies to you.
From India, Mumbai
Dear Mr Rawat,

Kindly go through my opinion dated 15th January 2022 on CiteHR.

https://www.citehr.com/632331-bocw-c...cation-machine.

With regards,
Chandra Mani Lal Srivastava
Master Consultant 9315516083

New Delhi
29.05.2022/9:25pm

From India, New Delhi
Hi Rawat The link is not working. Please check if there was a mistake
From India, Mumbai
I have posted my opinion on this subject in my blog a few months back. Please follow the link.

Madhu T K: Applicability of Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act to Factories

Madhu T K

From India, Kannur
Community Support and Knowledge-base on business, career and organisational prospects and issues - Register and Log In to CiteHR and post your query, download formats and be part of a fostered community of professionals.





Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2024 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.