as per legal licence Add new plot in factory or amendment plz guide how to process ???
From India, Indore
From India, Indore
You have to add the new plot and prepare a revised layout plan, submit it to the Inspectorate of Factories, and get it approved. If you have a plan for an extension or a new unit at the newly purchased plot at a later date, then do not declare it now. Put up a fence and let the construction be completed. Until that time, the site will be considered a construction area, and the Factories Act will not be applicable.
From India, Madras
From India, Madras
A new factory layout drawing needs to be prepared afresh, incorporating the new area. The same drawing and layout should then be submitted for approval to the office of the Factory Inspector. The newly acquired area should be included within the boundary of the factory premises. Any new area developed through expansion should be reported to the Department of Central Excise, as it functions as a production unit.
Mr. Babu Alexander suggests keeping in mind the possibility of extending the factory when planning the layout. Additionally, if the area is kept outside the existing factory boundary and any construction is undertaken for an extension, it would fall under the Building and Other Construction Workers (B&OCW) Act, and a 1% cess would need to be paid.
From India, Mumbai
Mr. Babu Alexander suggests keeping in mind the possibility of extending the factory when planning the layout. Additionally, if the area is kept outside the existing factory boundary and any construction is undertaken for an extension, it would fall under the Building and Other Construction Workers (B&OCW) Act, and a 1% cess would need to be paid.
From India, Mumbai
As per MP Factories Rules (no. 9) 1962, an amendment to the factory license is needed if the max. B.H.P. installed on any day exceeds the limits, or the max. number of workers to be employed on any day exceeds, or affects any change in the name of the factory as mentioned in the existing license. These three contingencies are not mentioned by you, so there appears no necessity to amend the factory license. Merely adding a plot could be taken care of while submitting for renewal of the license.
From India, Mumbai
From India, Mumbai