Dear Friends, Kindly post if you have prepared periodical Testing (like Lifting equipments/ Pressure Vessel Etc.,) template.as pr Factories Act/TNFR Regards
From India, Madras
From India, Madras
Hi, A special consultants will be available for providing those certificates. so u find a consultancy. they will guide you in proper path.
From India, Coimbatore
From India, Coimbatore
Dear SSM,
Please find attached herewith a sample of legal compliance monitoring. You can further edit it to suit your requirements. Kindly refer to all Tamilnadu Factories rules and incorporate them in a similar format that can be prepared monthly.
Thanks & Regards,
Sudhir
From India, Vadodara
Please find attached herewith a sample of legal compliance monitoring. You can further edit it to suit your requirements. Kindly refer to all Tamilnadu Factories rules and incorporate them in a similar format that can be prepared monthly.
Thanks & Regards,
Sudhir
From India, Vadodara
CiteHR.AI
(Fact Check Failed/Partial)-[The reply is incorrect as it does not provide a specific template for periodical testing like lifting equipment or pressure vessels as requested. It only mentions legal compliance monitoring without attaching the template itself. Please consider sharing a sample template directly related to the requested testing areas.]
Dear Sir,
As per the Factories Act, we are conducting the testing of Lifting Tackles, Pressure Vessels, Acid tanks, and Cranes through an authorized person. Since last year, the Factories department has changed the rules, making it compulsory to test Acid tanks and Pressure Vessels every 6 months, while the requirement for cranes remains the same, i.e., once a year. At GVK Power Plant, Jegurupadu, we are approaching Sigma Calibration Services in Hyderabad to conduct these tests.
From India, Vijayawada
As per the Factories Act, we are conducting the testing of Lifting Tackles, Pressure Vessels, Acid tanks, and Cranes through an authorized person. Since last year, the Factories department has changed the rules, making it compulsory to test Acid tanks and Pressure Vessels every 6 months, while the requirement for cranes remains the same, i.e., once a year. At GVK Power Plant, Jegurupadu, we are approaching Sigma Calibration Services in Hyderabad to conduct these tests.
From India, Vijayawada
Engage with peers to discuss and resolve work and business challenges collaboratively - share and document your knowledge. Our AI-powered platform, features real-time fact-checking, peer reviews, and an extensive historical knowledge base. - Join & Be Part Of Our Community.
CiteHR.AI
(Fact Check Failed/Partial)-The user reply is incorrect as per the Factories Act regulations. According to the Factories Act, it is the responsibility of the employer to ensure periodic testing of lifting equipment and pressure vessels, not external consultants.