Dear Saurabh,
Shops & Establishment Act is a State Act & therefore first see which is your State Shops Act which is applicable in your case & thereafter go through the relevant Rules to have all forms for your use.
[SIZE=1]R.N.Khola
[B][COLOR=#3366ff][FONT=Verdana]
[QUOTE=SAUR1309;1360182]Dear
Can u pls send me all forms under shop & establishment ACt, 1962
Thanking & Regards
Saurabh

From India, Delhi
anbu loganathan
Dear Members,

Thank you for your contributions on the subject. I am HR Manager working in Construction Company in Tamilnadu. Following are few questions about Registration under BOCW.

1. Whether the principal employer has to send Form I for registration or Contractor or both. (Recently I approached the authorities they have collected Form I from both alongwith fees) Is it permissible under the Act.

2. As a construction Company, we have various work sites. We have to get RC separately for each and every site or in total.

3. For new factory construction, RC in BOCW is enough or Both BOCW & CL(R&A) is required. In Tamilnadu DCIF is demanding BOCW & IL is demanding CL Act. in one particular work how both can have authority. Principal Employer not issued Form V stating that BOCW is superior ACT than the CL Act.

4. Any addition and Maintenance works in the existing manufacturing factories, Whether we have to register under BOCW or CL(R&A) Act or both.

5. We have applied for RC under BOCW even after 3 months we have not received any communication from the Authorities. We started work since Principal employer has got RC. In this case who has to submit Commencement in Form IV.

I expect opinions from the experts.

Regards & Thanks,

Anbu Loganathan

Manager HR

99623 91925

mail:

From India, Madras
V. Balaji
100

Mr. A. Loganathan,

Being in construction industry you might be aware of the Acts apply to you than anybody else, I trust.

1. Contract Labour (Regulation and Abolition Act) applies to one wherein 20 or more people are/were on any day during the last 12 months.

2. Whereas to apply BOCW Act, it is enough that > 10 employees are/were employed.

3. As per the above Acts, it is OK either Principle employer or the Contractor has to register under these Acts.

4. However, some cases, it is better the contractor (if you are one) complies with registration formalities for your own safety.

5. You know the Government Authorities, approach the issues - with respect to complying labour laws - and they go by what the Act says. They unnecessarily issue notice, etc. even they go to an extent of prosecuting it. So why do we take chance?

6. Form I pertains to the principle employer. It is nothing to do with (you) contractor. Principle employer has to apply for registration under the CLRA Act wherein he submitted Form I and remitted necessary fees. It is his scope of work.

7. Your job involves submitting Form IV, along with form V. Principle employeer cannot say that he cannot issue FORM V. As a contractor, when there are more than 20 employees employed in your site, you are required to obtain license and you need to apply for the same in FORM IV. And you need to pay "Security Deposit" and also remit some amount according to the no.of people you employ at your site. If you do not do that (stating that the principle employer is not issuing FORM V), then there would be loss to the "exchequer" in terms of revenue under CLRA Act. When it involves money matter, the CLRA authorities will not spare you. They will prosecute you and put interest, penalty, etc. Why should we give room for that?

7. You do not worry about non receipt of Registration Certificate under BOCW Act. It is your duty to apply for registration, which you have done promptly. When you send Form IV (under BOCW Act), mention in the appropriate column, "Registration has already been applied for you are yet to get the Certificate". Normally, it is presumed that within 90 days if you do not get any response from there, it is deemed to have been approved.

8. As far maintenance of registers are Concerned, you can write to the Officers concerned and obtain permission (there is provision in the Act) to maintain "single set of registrs" that will take care of both CLRA and BOCW Act. The format of these registers are almost one and the same.

thanks,

V. Balaji

From India, Madras
anbu loganathan
Dear Mr.V.Balaji,
Thank you verymuch for your detailed reply. Still I need some clarity, sorry to disturb you.
Your Point No.7. Regarding Form V
The maximum No. of employees proposed for the is 300 on any particular day. The project cost is around 20 C. The job is construction of Factory. The Registering authority called both Principal Employer & also Contractor. After a detailed discussion he orally told both of us BOCW is sufficient. Based on this statement Principal employer is not issuing Form V under CL Act. For new factories Inspector of Labour under Commissioner of Labour is the authority. When I happened to meet the IL he is telling no such notice from the Government.
Mr.Balaji, if you are in tamilnadu you know the real problem what I am explaining. Can you please communicate your contact particulars.
Regards,
Anbu Loganathan,
Manager HR
99623 91925.
mail:

From India, Madras
V. Balaji
100

Mr. A. Loganathan
Yes, that is what I am saying.
I strongly feel, you are required to register under both the Act. There are two different Govt. authorities involved in your case.
If you have a closer look at the Acts,
1. BOCW Act - they charge only registration charges, and nothing else.
2. CLRA Act - they charge you with (Refundable) Security Deposit and there is license fee involved in it.
If you go by the BOCW authority, IL from Office of Commissioner of Labour will sit on you for not taking license and not paying license fee.
So, plese talk to your principle employer. I do not understand why he should hesitates to issue form-V, by issuing the same, he is under no obligation. You convince him and obtain form V and register under CLRA Act. That would save you later.
by the way, I am in Chennai, My contact phone no. is 9941460342. You can cotact me.
Balaji

From India, Madras
Community Support and Knowledge-base on business, career and organisational prospects and issues - Register and Log In to CiteHR and post your query, download formats and be part of a fostered community of professionals.






Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2024 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.