Hi Good Morning....
Please Help me...
i Want to give a warning letter to a constructon company, because they fail to finish our showroom work on time. i want to ask them that, they have to pay one month rent as penalty....
Thank You.....
From Qatar, Doha
Please Help me...
i Want to give a warning letter to a constructon company, because they fail to finish our showroom work on time. i want to ask them that, they have to pay one month rent as penalty....
Thank You.....
From Qatar, Doha
Dear Shan Abu,
Have you made proper contract with the construction company? If yes, then have you inserted clause on the delay or deficiency in services? If this clause is not inserted or if the contract itself is not made then serving warning letter to the contractor will become inconsequential.
Delay in completion of the work by interior designing companies or construction companies is quite common. Therefore, some delay is condonable.
In view of this, I recommend you writing the warning letter on your own and uploading it here. Some senior like me will correct it.
Thanks,
Dinesh Divekar
From India, Bangalore
Have you made proper contract with the construction company? If yes, then have you inserted clause on the delay or deficiency in services? If this clause is not inserted or if the contract itself is not made then serving warning letter to the contractor will become inconsequential.
Delay in completion of the work by interior designing companies or construction companies is quite common. Therefore, some delay is condonable.
In view of this, I recommend you writing the warning letter on your own and uploading it here. Some senior like me will correct it.
Thanks,
Dinesh Divekar
From India, Bangalore
Please Check This
To,
General Manager
Happy Home Kitchen
Subject: Work Completion Notice
We hereby bring to your attention that as per your contract(HH/2013/14-15) with us , work completion date was 30/01/2016.After observing work progress we decided to give you 15 days additional (which will end 15/02/2016).
We ask to complete the work & handover the key on 15/02/2016. If you fail to do so you have to pay the showroom rent Qr.1666/- for each day until you finish the work.
From Qatar, Doha
To,
General Manager
Happy Home Kitchen
Subject: Work Completion Notice
We hereby bring to your attention that as per your contract(HH/2013/14-15) with us , work completion date was 30/01/2016.After observing work progress we decided to give you 15 days additional (which will end 15/02/2016).
We ask to complete the work & handover the key on 15/02/2016. If you fail to do so you have to pay the showroom rent Qr.1666/- for each day until you finish the work.
From Qatar, Doha
Dear Shan Abu,
The revised format is as below:
+++++
To,
The General Manager
______________
______________
In view of this, we hereby request you to complete the work & handover the key by 15/02/2016. If you fail to do so, showroom rent @ Qr.1666/- per day will be deducted from the balance payment.
Forwarded for information.
_________________
Authorised signatory
+++++
Dinesh Divekar
From India, Bangalore
The revised format is as below:
+++++
To,
The General Manager
______________
______________
Notice for Incomplete Work
We hereby bring to your attention that as per your contract (HH/2013/14-15) dated ______ with us , the contract work should have been completed by 30/01/2016. Recently we have reviewed the progress of the work and we found it incomplete. To give you chance to finish the work, it has been decided to give you 15 more days.In view of this, we hereby request you to complete the work & handover the key by 15/02/2016. If you fail to do so, showroom rent @ Qr.1666/- per day will be deducted from the balance payment.
Forwarded for information.