Dear Friends,
I need your help.
My company is planning to implement a 2-day week-off plan, and we are having difficulty making it a success in the manufacturing division for our staff. I have been working on this and have a solution, but not completely. I would like to ask for your help with the same.
This is the scenario:
The company is involved in manufacturing construction chemicals, covering an area of 100,000 square meters with 6 plants, 110 workers, operators, engineers (7), and a production manager.
All the engineers are trained to handle all the stations, but one engineer has to be always in the day shift as he looks after the ERP systems.
So now, leaving the manager aside and the ERP guy; we have 5 engineers who have to come in a rotational shift (3 shifts) and look after 6 plants. We need it to be done for 5 days.
I have planned in such a way that engineers will work on all the days, taking their 2 days week off without any extra cost, by following the roster system.
I need your help to modify my schedule and guide me accordingly. Your immediate response will be highly appreciated.
Thank you,
Mr. Amrut
I want to implement a 5-day working plan (schedule) on a rotational basis. I would like to present my company scenario. Please see the schedule attached and help me out.
Mr. Raj
Production Executive
From Saudi Arabia, Dammam
I need your help.
My company is planning to implement a 2-day week-off plan, and we are having difficulty making it a success in the manufacturing division for our staff. I have been working on this and have a solution, but not completely. I would like to ask for your help with the same.
This is the scenario:
The company is involved in manufacturing construction chemicals, covering an area of 100,000 square meters with 6 plants, 110 workers, operators, engineers (7), and a production manager.
All the engineers are trained to handle all the stations, but one engineer has to be always in the day shift as he looks after the ERP systems.
So now, leaving the manager aside and the ERP guy; we have 5 engineers who have to come in a rotational shift (3 shifts) and look after 6 plants. We need it to be done for 5 days.
I have planned in such a way that engineers will work on all the days, taking their 2 days week off without any extra cost, by following the roster system.
I need your help to modify my schedule and guide me accordingly. Your immediate response will be highly appreciated.
Thank you,
Mr. Amrut
I want to implement a 5-day working plan (schedule) on a rotational basis. I would like to present my company scenario. Please see the schedule attached and help me out.
Mr. Raj
Production Executive
From Saudi Arabia, Dammam
Two days off in a week is not good. You can also shift the day off every week. I mean to say that, for example, an employee is having a day off on Thursday in the first week of November. In the second week, he will be having it on any other day. We must compulsorily shift; they are not admin employees to have a specific day off. When we shift it every time, they will also feel happy.
The second thing I saw is you must give two days off in a week. It's absolutely wrong. Make shifts like 8 am to 2 pm, 2 pm to 8 pm, and in the night 8 pm to 8 am.
Any help you can provide on mobile: 9666346626.
From India, Chennai
The second thing I saw is you must give two days off in a week. It's absolutely wrong. Make shifts like 8 am to 2 pm, 2 pm to 8 pm, and in the night 8 pm to 8 am.
Any help you can provide on mobile: 9666346626.
From India, Chennai