No Tags Found!

Dear Friends
I have 625 KVA Diesel Generator ( Accostic) which is installed outside in open ie. Open air installation or outdoor installation . Recently to prevent from rain , The Engineering department is made a shed over it , Now is this change is reported to factory inspector as now it is covered through Roof , From other all side it is open -
& Second what about Fire Protection - Is this shed need to be covered through Fire Protection ie Minimum control through by Fire Extinguisher .
Friends do reply on this
Regards

From India, Pune
Dear Jagjeetsingh.Aroraunileve,

Discussion you invited has so many aspects. We as HR professionals, at least I, are not experts in such kind of technical issues. Bear in mind, half knowledge is very dangerous.

However, this forum is meant for enhancing knowledge by sharing, I would like to participate in the discussion.

You have installed 625 KVA Diesel Generator ( Accostic) in the premises of your factory. It seems to me, this DG set is installed as per the approved plans of machinery lay out and now you have made the change in it by erecting shed on it. Under this scenario it is presumed that:

i. you must have followed the norms under the Petroleum Rules 2002, Explosive Rules for storage of diesel etc.;

ii. you must have complied the provisions under Local Body Act such as Municipal Act in respect of trade / use and storage of diesel, fire protection, provisions under Environmental Law etc.;

iii. you must have obtained the permission for the use of D.G. Set under Electricity Supply Act, 1948.

Now the change of erection of shed has to be incorporated in your approved plans. You need to apply for it by submitted fresh plans.

When you submit the fresh plans for approval by the Factory Inspector, the approve will be given to you subject to certain conditions as deem fit to him i.e. to factory inspector, such as requirement of fire extinguishers, NOC from fire brigade, NOC under Environmental Law etc.

From India, Mumbai
Mr. Jagjeetsingh, Please note that this is a forum for handling Human Resources related issues and problems as well as discussions. You have posted a problem, not relevant to this site at all. Talk to the person or company related to the DG Set such as Kirloskars or somebody.
Best wishes

From India
Sharing my views on this post - that having knowledge on statutory aspect of the technical installation is something which is essential to all. Second if the issue is on sharing the information on safety and security of people we must welcome.There are many contributors who may have good knowledge and like to share with us.
As regards to the query -
Earthing, Loose connection, open cable layouts, improper fuel storage Etc are the causes that may pose fire threats/electrification threats.
To prevent from any fire incidents - the supplier usually provided fire extinguishers along with DG sets.However added precautions will be required to keep extra fire extinguishers near the DG set.Fire Buckets /sand buckets/fire beater etc may be kept as tools to fight fire in case of emergencies.Suggest deputation of expert to monitor DG set when its running.
Apart from this as Mr. Korgaonkar Sir Indicated - statutes/norms related to such installations to be adhered strictly.

From India, Vadodara
Dear keep sand bucket and fire extinguisher near D.G. set to avoid fire threat and get it approve from the fire dept. also get it incorporated in the earlier fire load /plan submitted during the NOC from the dept.
Installation formality is well known to vendor who install DG set in factory.

From India, Chandigarh
Dear,
Please write your query in in top left corner near to Cite HR logo having Box "What do you need" and click on "research" button, you will find lots of discussions/views which is contributed by experts in Cite HR forum.

From India, Ahmadabad
Dear Jagjeet,
As per my knowledge first of all, you will check its a permanent shed or temporarily.
First you take permission from local body for temporary shed.
or is this permanent shed then you have to take permission form factory inspector with changes in factory plan.
I hope your problem will be solved.
Thanks & Regards,
Bhupesh Parab

From India, Thane
ask your insurance company to survey the site of DG set whether safety precautions taken are sufficient and if not what needs to be done. There are safety auditors also who are authorized to carry out such survey and report deficiency and measures to be taken to rectify defects if any.
A S Bhat

From India, Pune
Dear JAGJEETSINGH.ARORAUNILEVE
First You need Statutory requirement for Installation of DG . Fire fighting facilities at DG room different different for various industry but as per OISD for oil and gas industry 2Nos of 10kg DCP type fire extinguisher and 2nos of 4.5kg CO2 type fire extinguishers are required.
With Regards
Mukesh Singh rathour

From India, Chennai
Community Support and Knowledge-base on business, career and organisational prospects and issues - Register and Log In to CiteHR and post your query, download formats and be part of a fostered community of professionals.





Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2024 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.