Mohamed Haneef
Can anyone help me in the following issue:
I am working in Construction Company. Wherever we get a contract to construct buildings, the principal Employer has to pay the CESS to the Government as per Building and Other Construction Act. Since the principal employer is paying CESS, ESI is applicable or not? If not, is it applicable to all the workers (Principle employer, Contractor, Sub-contractors etc). Also please let me know how the workers can get the benefit from this Building and Other Construction Act.
Regards,
Haneef

From India, Bangalore
INSAKN
Subject- Applicability of BOCW Act/rules
For therrmal Power plant -during construction phase whose site Site plot and building plans have been approved under The Factories Act, whether BOCW act will still be applicable ? or will come under purview of the Factories rules itself.
request for clarification.
thanks!
Sanjeev

From India, Mumbai
boss2966
1168

Dear Haneef
Please go through the earlier discussed thread https://www.citehr.com/344521-buildi...lrker-law.html
Hope it will clear all your doubt
If you have any further any querry in the subject never hesitate to contact.

From India, Kumbakonam
Community Support and Knowledge-base on business, career and organisational prospects and issues - Register and Log In to CiteHR and post your query, download formats and be part of a fostered community of professionals.





Contact Us Privacy Policy Disclaimer Terms Of Service

All rights reserved @ 2024 CiteHR ®

All Copyright And Trademarks in Posts Held By Respective Owners.